Skip to content

Other Projects

Current and Upcoming Construction Projects

Maintaining and improving our wastewater treatment systems is an ongoing effort that requires many capital construction projects. These projects take place at the Budd Inlet Treatment Plant, offsite facilities, pump stations and LOTT’s sewer interceptor pipelines. LOTT has multiple capital projects underway at any one time. Check back occasionally for updates on ongoing and upcoming projects.

Construction Crane

LOTT Construction Impacts

Some construction projects may cause disruptions beyond LOTT property boundaries. When construction is likely to cause disruptions, LOTT strives to alert residents and business owners who may be affected.

North Pipeline Upgrades

This project upgrades a 1,250-foot section of north outfall pipeline from 30-inch to 48-inch diameter pipe to increase hydraulic pumping capacity. The pipeline runs north from the treatment plant, through the Port of Olympia log yard and Cascade Pole site, to the northernmost point of the Port of Olympia. Construction is expected to begin in the summer of 2026.

Digester System Improvements

In early 2025, LOTT Clean Water Alliance will begin a major construction project to refurbish the digester system at the Budd Inlet Treatment Plant. Work includes new digester covers and replacement of the emergency waste gas burner with an enclosed flare. Construction will occur in stages over a three-year period with anticipated completion in early 2028.

Centrate Building Rehabilitation

This project includes partial demolition and rehabilitation of the Centrate Building. Construction began in early 2024 and will continue through early 2025. Work involves removing the roof, repairing, and repainting structural steel, replacing air handling and odor control systems, modifying pipes, replacing doors and windows, reroofing of the building, and adding a solar array.

Martin Way Pump Station Upgrade

The LOTT Clean Water Alliance Martin Way Pump Station was constructed in the early 1990s to convey flow from the City of Lacey to the Budd Inlet Treatment Plant. This project will replace aging equipment and upgrade the system based on observed and predicted capacity increases. The pre-design phase is currently underway.

Security Improvements

Installation of new fencing around the treatment plant perimeter, LOTT offices, and the East Bay Public Plaza was completed in 2022. A follow-on project to replace two vehicle gates is scheduled for later this year. These efforts will result in greater security of the Budd Inlet Treatment Plant and related facilities.